What happened
Wynn Resorts has moved the opening of Wynn Al Marjan Island to September 2027, from the first quarter of the same year. Chief executive Craig Billings announced it on the second-quarter call with analysts, and Khaleej Times published the details on 5 August 2026. CDC Gaming Reports carried the same statement in its results coverage.
Billings said the regional conflict first disrupted global supply chains and is still affecting the shipping insurance market. Some materials and equipment had to be re-sourced, rerouted or expedited to protect the schedule. The movement of staff and consultants was also disrupted, along with other non-recurring issues.
The numbers
The company raised the total project budget by roughly USD 600 million, about AED 2.2 billion. According to Billings, about half of the increase comes directly from the conflict: higher material and shipping costs, plus the pre-opening and capitalised interest costs created by a longer build. The rest reflects remeasurement, trade coordination and other costs one would expect on a project of this scale and duration, regardless of events in the region.
Wynn Resorts holds 40 per cent of the joint venture building the resort. In the second quarter it contributed USD 48.1 million in cash, about AED 176.5 million, bringing its contributions to date to USD 1.06 billion. For comparison, earlier reports put the budget at USD 5.1 billion before this revision.
Where construction stands
Billings said interior work in the hotel rooms had begun, with mechanical, electrical and finishing trades moving in sequence, and that pre-opening hiring and operations planning were advancing well. He added that he had visited the site in June and found flights full and day-to-day activity in Dubai healthy.
The revision lands on a project that was already well advanced. By December 2025, 67 per cent of the USD 5.1 billion budget had been spent or contractually committed, and the tower had reached its structural top at 283 metres across 70 floors, as AGB reported. In February Wynn had guided to USD 375 million to USD 400 million of equity contributions in 2026 and USD 75 million to USD 100 million in 2027, according to Khaleej Times; the August revision came after that guidance.
Our reading
What I find useful here is that the company split the increase into two causes instead of blaming all of it on the war. Half is circumstantial; the other half would probably have appeared anyway. A delay of about six months is also shorter than some expected when reports of a postponement surfaced in May.
Timeline
- Early 2023Construction begins
- October 2024The UAE’s first commercial gaming facility licence
- December 2025The tower tops out
- March 2026Construction resumes after a short pause
- 5 August 2026New opening date and budget increase announced
- September 2027Planned opening
What changes for UAE readers
No licensed land-based casino will open in the UAE before September 2027 at the earliest. Any claim before then of a “casino now open” in the country does not refer to this resort.
For the current legal framework, see our legal status page; to follow the project, see all Al Marjan Island news.
Compiled from public reporting; see the linked outlets above. Informational, not legal advice. 21+.