Al Marjan Island casino news

Wynn Q3 2026: all Al Marjan rooms now in interior fit-out

Wynn Resorts says interior fit-out has started in every guest room at Wynn Al Marjan Island, and the September 2027 opening date has not moved. The group’s own quarter was weaker, which tells us little about the resort itself.

Wynn Las Vegas, the group’s flagship resort. Illustrative photo; it does not show the Ras Al Khaimah project.
Wynn Las Vegas, the group’s flagship resort. Illustrative photo; it does not show the Ras Al Khaimah project. Photo: Alexander Migl / Wikimedia Commons, CC BY-SA 4.0
Planned opening
September 2027
Group operating revenue, Q3 2026
USD 1.69 billion
Net income attributable, Q3 2026
USD 17.3 million

What happened

Wynn Resorts published its third-quarter 2026 results on 5 November. In the part that concerns the UAE, chief executive Craig Billings said the Wynn Al Marjan Island team had made substantial progress, with finishing work running throughout the property and the interior fit-out of all guest rooms under way. The planned opening stays at September 2027. CDC Gaming Reports carried the statement in its write-up of the results the same day.

It is a short paragraph inside a long earnings release, but it is the first time the company has described fit-out as covering every room. Three months earlier, on the second-quarter call, Billings spoke of interior work starting in the hotel rooms, with mechanical, electrical and finishing trades moving in sequence, as Khaleej Times reported on 5 August.

The numbers

The group figures were weaker than a year ago. Operating revenue was USD 1.69 billion against USD 1.83 billion in the third quarter of 2025, a fall of USD 144.7 million. Net income attributable to Wynn Resorts dropped to USD 17.3 million from USD 88.3 million, or USD 0.17 per diluted share against USD 0.85. Adjusted property EBITDAR, the measure of operating cash flow the industry prefers, came in at USD 464.2 million, down USD 105.9 million.

Revenue fell at every operating resort: by USD 51.7 million at Wynn Palace, USD 45.8 million in Las Vegas, USD 30.1 million at Wynn Macau and USD 17.1 million at Encore Boston Harbor. Billings pointed to a Las Vegas hold rate outside the expected range and to a strike in Boston that began in early September.

Why the group results do not describe the resort

None of these figures comes from Ras Al Khaimah. Wynn Al Marjan Island has no revenue yet, and Wynn accounts for it as a 40 per cent share in a joint venture rather than as an operating property. The UAE number that matters is the cash Wynn puts into that venture: USD 48.1 million in the second quarter of 2026, which took its contributions to date to USD 1.06 billion, according to the August reporting.

The resort is planned around 1,530 rooms and suites, 22 food and beverage venues, a theatre, luxury retail and a marina in a 70-storey tower, as Khaleej Times described it in March. Over the summer Wynn also named some of its partners: the paper listed the immersive theatre company Punchdrunk, a restaurant by the chef Alain Ducasse and the first international venue of Delilah, the Las Vegas supper club.

Our reading

In my reading, the useful signal in this release is that nothing moved. The date that shifted once, from the first quarter to September 2027, held through a quarter in which the group had plenty of bad news to report. Fit-out of every room is the stage at which a hotel project stops being about structure and starts being about systems, staffing and operational readiness. The next checkpoint is the fourth-quarter release.

Timeline

  1. October 2024The GCGRA issues the UAE’s first commercial gaming facility licence to the venture
  2. December 2025The tower tops out
  3. August 2026Opening moved to September 2027; budget raised by about USD 600 million
  4. 5 November 2026Q3 results: fit-out of all guest rooms under way
  5. September 2027Planned opening

What changes for UAE readers

Nothing changes yet for residents: no licensed land-based casino operates in the UAE, and the opening is still almost a year away. When the resort opens, it will run under a licence from the federal regulator, the GCGRA, which limits licensed gaming to people aged 21 and over.

For what is and is not lawful today, read our legal status page and the guide to UAE law and online gambling.

Compiled from public reporting; see the linked outlets above. Informational, not legal advice. 21+.

Responsible gambling

Play for entertainment, within limits

Gambling is for adults only (21+) and always carries risk. These habits help keep it within the limits of entertainment.

  • Set a deposit limit

    Decide before you play how much you can spend without it affecting you, per day, week or month.

  • Use reminders

    A reminder every 30 or 60 minutes shows how long you have played and what you have spent.

  • Take a break

    Time-outs and self-exclusion lock your account for days or months, and cannot be undone early.

  • Watch for the signs

    Chasing losses, hiding your play, borrowing to play or feeling anxious when you stop are signs to ask for help.

Need to talk to someone? Talk to a doctor or a counsellor you trust. The responsible gambling page gathers practical steps to set limits or stop.