What happened
Wynn Al Marjan Island announced that its tower had topped out, calling it a defining milestone for the UAE’s first integrated resort. AGB carried the announcement on 16 December 2025: the tower had reached 283 metres across 70 floors, just 27 months after foundation work began.
According to the statement, all structural concrete for the tower was complete and nearly all guest-room structures were finished as of late November 2025. Once its spire is installed in 2026 the tower will reach 352 metres, the tallest man-made structure in Ras Al Khaimah by more than 100 metres. The project said at the time that it was on track to welcome guests in spring 2027.
The numbers
Wynn Resorts said 67 per cent of the project’s USD 5.1 billion budget had been spent or contractually committed. The company estimates the UAE could generate USD 3 billion to USD 5 billion a year in gaming revenue once three integrated resorts are operating, and expects Wynn Al Marjan Island alone to produce USD 1 billion to USD 1.7 billion in gross gaming revenue at steady state.
It projects annual property EBITDAM of USD 500 million to USD 800 million, which implies a project return of 9.8 to 15.7 per cent and a return on equity of 16.7 to 34.3 per cent after a ramp-up that typically lasts three years. These are the company’s own projections, not results.
How the tower got here
Construction began in early 2023, according to Khaleej Times, which in October 2024 expected a 300-metre tower to top out in the fourth quarter of 2025. In February 2025, 64 per cent of the structural concrete was complete up to the 34th floor and the crews were finishing one floor a week, as Gulf Construction reported from the company’s statement.
The Wikipedia entry for the resort summarises the published plans: a main casino of 20,900 square metres, 22 restaurants, 12,000 square metres of retail, 7,708 square metres of convention space and a second casino on the 22nd floor. In February 2025 the company described a resort of 1,542 rooms and suites, 50 minutes from Dubai International Airport, according to AGB.
Our reading
Topping out on time was the clearest evidence so far that the project was running to plan. The return figures I read as investor-facing ranges: the distance between their low and high ends is wide, and that in itself tells you how hard it is to size a market that has never operated. The gap between project return and return on equity is explained by debt: in February 2025 the venture took a USD 2.4 billion construction loan.
Timeline
- Early 2023Construction begins
- February 202564% of structural concrete done, up to the 34th floor
- Late November 2025All tower structural concrete complete
- 16 December 2025Topping out announced
- 2026Spire installation, per the plan
- Spring 2027Guest arrivals targeted at the time
What changes for UAE readers
A finished tower does not mean a working casino. The opening was later moved to September 2027, and until then no licensed land-based casino operates in the UAE.
For the licence the project works under, see the story on the first commercial gaming licence; for the legal framework, our legal status page.