What happened
Wynn Resorts released its fourth-quarter and full-year 2025 results on 12 February 2026. Chief executive Craig Billings said the company had reached a significant milestone toward the opening of Wynn Al Marjan Island, having topped out the tower during the quarter, and the company’s report said construction remained on schedule with extensive interior work under way. Khaleej Times published an analysis of the resort figures on 15 February, and CDC Gaming Reports covered the results on the day.
The stated opening at the time was the first quarter of 2027. The resort was then a USD 5.1 billion project, about AED 18.7 billion, with a 70-storey tower, 1,530 rooms and suites, 22 food and beverage venues, a theatre and a marina.
The numbers
In the fourth quarter Wynn contributed USD 79.2 million in cash to the joint venture it owns 40 per cent of, bringing its contributions to date to USD 914.2 million. It expected to put in USD 375 million to USD 400 million of equity in 2026 and USD 75 million to USD 100 million in 2027, and estimated its remaining equity contribution at USD 450 million to USD 550 million.
On the return side, the company expects the resort to add about USD 345 million to its EBITDAR, made up of its share of cash flow and management fees. In 2025 Billings had estimated the country’s gross gaming revenue at USD 3 billion to USD 5 billion a year, said he expected two additional competitors, and added that with no announced competition so far the estimates were probably conservative.
The group in 2025
Net income attributable to Wynn Resorts was USD 327.3 million for 2025, against USD 501.1 million in 2024. Operating revenue for the year was USD 7.14 billion, against USD 7.13 billion, and adjusted property EBITDAR was USD 2.22 billion, down from USD 2.36 billion. Fourth-quarter revenue alone was USD 1.87 billion, against USD 1.84 billion a year earlier, while net income attributable fell to USD 100 million from USD 277 million. Those are results from resorts operating in Macau, Las Vegas and Boston, and they say nothing about the Ras Al Khaimah project, which has not opened.
Our reading
The key point in these numbers is that most of Wynn’s equity in the project was paid before opening, and what remained sat in a clear range. Since the budget rose by about USD 600 million in August, it is reasonable to expect these figures to change in later releases, so we read them as February’s picture rather than a final commitment.
Timeline
- December 2025The tower tops out
- 12 February 2026Wynn reports Q4 and full-year 2025 results
- 15 February 2026Khaleej Times: construction on schedule for early 2027
- 5 August 2026Opening moved to September 2027
What changes for UAE readers
These figures matter more to Wynn’s investors than to readers in the UAE, but they show that the resort is funded and moving toward opening, and that the expected market is large enough to attract other operators later.
Any new operator would need a licence from the GCGRA; see our legal status page and the UAE gaming law news.