Wynn weighed an Al Marjan delay as Gulf conflict hit work

In May 2026 AGB, citing Bloomberg, reported that Wynn was considering a delay to its Al Marjan Island resort after the regional conflict disrupted construction and weakened tourism. Three months later the delay was confirmed: the resort now opens in September 2027.

Towers under construction at Dubai Creek. Illustrative photo, not the project site.
Towers under construction at Dubai Creek. Illustrative photo, not the project site. Photo: Jpbowen / Wikimedia Commons, CC BY-SA 4.0
Stated project cost at the time
USD 5.1 billion
Opening target at the time
Q1 2027
Planned hiring before launch
About 2,700 people

What happened

On 6 May 2026 AGB reported, citing Bloomberg, that Wynn Resorts was weighing a delay to the opening of its Al Marjan Island resort. According to the report, the presence of attack drones and missiles in the area had disrupted work and weakened tourism demand. At the time the resort was due to open in the first quarter of 2027, less than a year away.

The project, with a stated cost of USD 5.1 billion, is being developed by Wynn with local partners and is set to become the first casino resort in the region. In mid-March the company had said construction had resumed after a brief suspension, and that it was assessing construction materials awaiting delivery and looking at alternative ports for supplies.

Numbers and context

Before the recent tensions, Wynn had set out a plan to accelerate recruitment: about 2,700 hires before launch, with total staffing approaching 3,000 by December 2026. The report also noted that MGM Resorts International is developing a hotel project in Dubai, and that its chief executive Bill Hornbuckle said on an earnings call on 29 April that tourism in the region had weakened sharply and would take time to recover whatever happened.

A day after the report, on 7 May, Wynn released its first-quarter results. According to CDC Gaming Reports, Craig Billings said construction was continuing and that the company was watching the situation in the Gulf closely and taking additional precautions for the safety of its team on site. He gave no new date at that point.

What Wynn had said in March

The March statement, reported by Khaleej Times on 11 March, already hinted at the pressure. Wynn said it had taken steps for the safety of everyone working on site, that employees could work from abroad if their home embassy advised it, and that it was in regular contact with the UAE and Ras Al Khaimah governments. Any further impact on the project, it added, would be assessed in due course.

How it ended

The answer came on 5 August: an opening in September 2027 and a budget increase of about USD 600 million, roughly half of it tied to the conflict, according to Billings. The report that cited Bloomberg was right about the direction, and the actual delay came to about six months.

Our reading

The original report rested on unnamed sources and the company did not confirm it at the time, so we treated it as a possibility rather than a decision. What stands out in hindsight is that Wynn did not deny a delay in its May results; it spoke only about safety and continued work, wording that left the door open. The practical lesson for anyone following the project is that opening dates on projects this size move, and the reference point is what the company states in its quarterly results and official statements, not what circulates before them.

Timeline

  1. Mid-March 2026Wynn says construction has resumed after a short pause
  2. 29 April 2026MGM’s chief executive says regional tourism has weakened
  3. 6 May 2026Report that a delay is being weighed
  4. 7 May 2026Q1 results: construction continues with extra precautions
  5. 5 August 2026Opening confirmed for September 2027

What changes for UAE readers

The date that counts today is September 2027; earlier reports have been overtaken by events. Until then, no licensed land-based casino operates in the UAE.

If you see offers that claim a link to the resort before it opens, treat them with caution and check our legal status page and the warnings list.

Compiled from public reporting; see the linked outlets above. Informational, not legal advice. 21+.

Responsible gambling

Play for entertainment, within limits

Gambling is for adults only (21+) and always carries risk. These habits help keep it within the limits of entertainment.

  • Set a deposit limit

    Decide before you play how much you can spend without it affecting you, per day, week or month.

  • Use reminders

    A reminder every 30 or 60 minutes shows how long you have played and what you have spent.

  • Take a break

    Time-outs and self-exclusion lock your account for days or months, and cannot be undone early.

  • Watch for the signs

    Chasing losses, hiding your play, borrowing to play or feeling anxious when you stop are signs to ask for help.

Need to talk to someone? Talk to a doctor or a counsellor you trust. The responsible gambling page gathers practical steps to set limits or stop.